Question: please help The critical path in PERT/CPM is a sequence of connected nodes that lead from the Start node to the Finish node with the

please help

The critical path in PERT/CPM is a sequence of connected nodes that lead from the Start node to the Finish node with the most probable total time. the average total time. o the shortest total time. the longest total time. None of the above