Question: please help! The following information is known about a project. Activity A B D E F G H Immediate Predecessor(S) Activity Time 6 3 A
please help!
The following information is known about a project. Activity A B D E F G H Immediate Predecessor(S) Activity Time 6 3 A 2 B, C 3 c.b 6 E 3 B 9 F, G 3 . . Draw the network for this project. Calculate ES, EF, LS, and LF. Find the critical path for this project. What is the project completion time