Question: please help! The following network and respective activity times represent a project being analyzed by the critical path method. Which of the following are false?
The following network and respective activity times represent a project being analyzed by the critical path method. Which of the following are false? A. Activity J must be critical regardless of its activity duration B. The length of path ABEHJ is 20 C. The critical path is A-B-G-WJ D. Delaying activity C by two time units immediately delays the project duration by the same amount E. All of the above are false