Question: Using PERT, Adam Munson was able to determine that the expected project completion time for the construction of pleasure yacht is 21 months, and the
Using PERT, Adam Munson was able to determine that the expected project completion time for the construction of pleasure yacht is 21 months, and the project variance is 9 . a) The probability that the project will be completed in 12 months = (round your response to four decimal places). b) The probability that the project will be completed in 20 months = (round your response to four decimal places). c) The probability that the project will be completed in 24 months = (round your response to four decimal places)