Question: Please let me know If I did this correctly. I have one hour. In the following table the activities with their precedence sequence and expected

Please let me know If I did this correctly. I have one hour.

Please let me know If I did this correctly. I

In the following table the activities with their precedence sequence and expected time (days) are listed for a project on which Carl Betterton's construction company is working: Immediate Predecessor(s) Time (days) 4 6 Activity A B D E F G 6 A A B B D E, F 4 4 6 9 H Carl's team should be able to complete the project in 26 days. Critical path activities for Carl's project are A-C-F-H