Question: Please MARK THE CORRECT ANSWER based on the following table : ACTIVITY TASK DEPENDENCY DURATION in days A - 3 B A FF6 5 C
Please MARK THE CORRECT ANSWER based on the following table :
| ACTIVITY | TASK DEPENDENCY | DURATION in days |
| A | - | 3 |
| B | A FF6 | 5 |
| C | A FS 9 | 4 |
| D | B SS7; C | 8 |
- A.
Activity D may start at the same time as Activity B.
- B.
Activity D may start 7 days after Activity B has started.
- C.
Activity D may finish 7 days after Activity B has started.
- D.
Activity D may start 7 days after Activity B has finished.
- E.
Activity D may finish 7 days after Activity B has finished.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts