Question: Please MARK THE CORRECT ANSWER based on the following table : ACTIVITY TASK DEPENDENCY DURATION in days A - 3 B A FF6 5 C

Please MARK THE CORRECT ANSWER based on the following table :

ACTIVITY

TASK DEPENDENCY

DURATION in days

A

-

3

B

A FF6

5

C

A FS 9

4

D

B SS7; C

8

  • A.

    Activity D may start at the same time as Activity B.

  • B.

    Activity D may start 7 days after Activity B has started.

  • C.

    Activity D may finish 7 days after Activity B has started.

  • D.

    Activity D may start 7 days after Activity B has finished.

  • E.

    Activity D may finish 7 days after Activity B has finished.