Question: ***PLEASE PLEASE SOLVE BY HAND AND SHOW THE SOLUTION*** A work breakdown structure and expected durations for a project are as follows: [a] Create the
***PLEASE PLEASE SOLVE BY HAND AND SHOW THE SOLUTION***
A work breakdown structure and expected durations for a project are as follows:

[a] Create the AON network.
[b] Identify the CPM.
[c] Prepare a crash schedule to shorten the completion time by 2 weeks.
Activity Predecessor 1 2 3 4 5 6 7 8 Normal Duration 1 5 3 7 4 6 8 2 Shortest Duration Additional cost to crash (weeks) an activity (cost/week) 1 0 4 2,000 1 3,000 4 3,500 2 2,000 3 5,000 5 900 1 300 1 1 2,3 2 4,5 4 6,7 Activity Predecessor 1 2 3 4 5 6 7 8 Normal Duration 1 5 3 7 4 6 8 2 Shortest Duration Additional cost to crash (weeks) an activity (cost/week) 1 0 4 2,000 1 3,000 4 3,500 2 2,000 3 5,000 5 900 1 300 1 1 2,3 2 4,5 4 6,7Step by Step Solution
There are 3 Steps involved in it