Question: ***PLEASE PLEASE SOLVE BY HAND AND SHOW THE SOLUTION*** A work breakdown structure and expected durations for a project are as follows: [a] Create the

***PLEASE PLEASE SOLVE BY HAND AND SHOW THE SOLUTION***

A work breakdown structure and expected durations for a project are as follows:

***PLEASE PLEASE SOLVE BY HAND AND SHOW THE

[a] Create the AON network.

[b] Identify the CPM.

[c] Prepare a crash schedule to shorten the completion time by 2 weeks.

Activity Predecessor 1 2 3 4 5 6 7 8 Normal Duration 1 5 3 7 4 6 8 2 Shortest Duration Additional cost to crash (weeks) an activity (cost/week) 1 0 4 2,000 1 3,000 4 3,500 2 2,000 3 5,000 5 900 1 300 1 1 2,3 2 4,5 4 6,7 Activity Predecessor 1 2 3 4 5 6 7 8 Normal Duration 1 5 3 7 4 6 8 2 Shortest Duration Additional cost to crash (weeks) an activity (cost/week) 1 0 4 2,000 1 3,000 4 3,500 2 2,000 3 5,000 5 900 1 300 1 1 2,3 2 4,5 4 6,7

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!