Question: Question 5 A project work breakdown structure and expected durations are as follows: table [ [ Activity , table [ [ Normal ]

Question 5
A project work breakdown structure and expected durations are as follows:
\table[[Activity,\table[[Normal],[Duration]],\table[[Shortest],[Duration],[(weeks)]],\table[[Additional cost to],[crash an activity],[(cost/week)]],Predecessor],[1,1,1,0,-],[2,6,5,1,100,-],[3,2,1,2,200,1],[4,6,5,3,400,1],[5,3,2,2,200,2,3],[6,4,3,5,100,2,3],[7,6,5,450,4,5]]
[a] Create the AON network.
[b] Identify the CPM.
[c] Prepare a crash schedule to shorten the completion time by 2 weeks.