Question: Predecessor Question 2 A project work breakdown structure and expected durations are as follows: Activity Normal Shortest Additional cost to crash Duration Duration (weeks) an

Predecessor Question 2 A project work breakdown

Predecessor Question 2 A project work breakdown structure and expected durations are as follows: Activity Normal Shortest Additional cost to crash Duration Duration (weeks) an activity (cost/week) 1 0 2 5 4 1,100 3 3 2 2,400 4 5 3,200 5 3 2 2,200 6 4 3 4.000 7 6 5 600 6 2 1.2 3,4 3,4 5,6 [a] Create the AON network. [b] Identify the CPM. [c] Prepare a crash schedule to shorten the completion time by 2 weeks