Question: Please post the step by step tutorial, and bold the final answer 3. Using the data below, create the project schedule using normal times. Determine

Please post the step by step tutorial, and boldPlease post the step by step tutorial, and bold the final answer

3. Using the data below, create the project schedule using normal times. Determine the order in which you would crash the project one day, two days, and so on until it is in an all-crash mode. Identify how much it would cost for each day you crash the schedule. Activity Predecessor Normal Crash Cost Normal Cost Crash Time Crash Cost per Day Time A B 5 200 4 350 B 8 220 8 220 C B 6 250 4 650 D A 9 500 600 E A, C 10 150 500 F E 10 500 650 G D, F 8 400 900 5 9 9 6