Question: *Please provide the slack time for each A,B,C,D,E,F,G* Roger Ginde is developing a program in supply chain management certification for managors. Ginde has listed a
*Please provide the slack time for each A,B,C,D,E,F,G*
Roger Ginde is developing a program in supply chain management certification for managors. Ginde has listed a number of activities that must be completed beiore z iraini the accompanying table: This exorcise contains only parts b, c, and d: b) The critical activities for the leadership training program development project ate BDEC. c) The project length for the leadershlp training program development project =32 days. d) Slack time for each of the activities is