Question: PLEASE QUICKLY Given the following data, construct a material requirements plan for all components which will result in 80 units of (E) at the beginning
PLEASE QUICKLY
Given the following data, construct a material requirements plan for all components which will result in 80 units of (E) at the beginning of week 6. Here is the data: E B(2) J (3) J (2) Item Currently On- Hand Scheduled Receipt (wk) Lead time Order Quantity E 10 - 2 L4L B 50 10 (wk2) 2 Lot size 120 J 20 10 (wk3,4, 5) 1 Lot size 30 FORMAT USING A TABLE THIS Week Number 1 2 3 4 5 6 Gross Requirements Scheduled Receipts Projected on hand Net requirements Planned-order-receipt Planned-order release