Question: Q4. Given the following data, construct a material requirements plan for all components which will result in 80 units of end item (E) at the

Q4. Given the following data, construct a

Q4. Given the following data, construct a material requirements plan for all components which will result in 80 units of end item (E) at the beginning of week 6. E B (2) J (3) J (4) Item Currently On-Hand Scheduled Receipt (wk) Lead time Order Quantity E B J 10 50 20 2 2 10 (wk 2) 30 (wk 3,4,5) L4L Lot size of 120 Lot size 30 1