Question: Please review and answer the question. Solved Problem #1 p. 96 Immediate Predecessors - Activity A B C D E F G H I Days

Please review and answer the question. Solved

Please review and answer the question.

Solved Problem #1 p. 96 Immediate Predecessors - Activity A B C D E F G H I Days 1 4 3 7 6 2 7 9 4 A B CD E.F D G H a. Draw the critical path diagram (Activity-on-Node = AON). b. Show the critical path. c. How long does it take to complete the project? d. What would happen if activity F was revised to take four days instead of two? ET (a + 4*m+b) 6 VAR -((b-a) 6-2

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!