Question: Please review and answer the question. Solved Problem #1 p. 96 Immediate Predecessors - Activity A B C D E F G H I Days

Please review and answer the question.
Solved Problem #1 p. 96 Immediate Predecessors - Activity A B C D E F G H I Days 1 4 3 7 6 2 7 9 4 A B CD E.F D G H a. Draw the critical path diagram (Activity-on-Node = AON). b. Show the critical path. c. How long does it take to complete the project? d. What would happen if activity F was revised to take four days instead of two? ET (a + 4*m+b) 6 VAR -((b-a) 6-2Step by Step Solution