Question: please show all the work 13. VZ is considering two additional higher risk projects with a required rate of return of 12%. Based on the
13. VZ is considering two additional higher risk projects with a required rate of return of 12%. Based on the following cash flows which project should VZ choose and why? (7 points) NO Year Project 1 cash flow -320,000 115,000 159,000 3 132,000 Project 2 cash flow -260,000 35,000 58,000 249,000