Question: Please show all work 5. Consider the project with the following dependency matrix. Activity Predecessor Activity Time (day) 2 A1 A2 A1 4 A1 3

Please show all work 5. Consider the project withPlease show all work

5. Consider the project with the following dependency matrix. Activity Predecessor Activity Time (day) 2 A1 A2 A1 4 A1 3 A4 A1 2 A5 A2, A3 4 A6 A4, A5 5 A. Compute the earliest completion time of the project using EST and ECT. (15 Points) B. What is the total slack time(s) of the project? (15 Points)