Question: please show in EXCEL The plan for Project BX802 shows the following summary information: Activity A, IP = none, Duration = 5 weeks, BC =

please show in EXCEL The plan for Project BX802please show in EXCEL
The plan for Project BX802 shows the following summary information: Activity A, IP = none, Duration = 5 weeks, BC = 9000 dollars/week Activity B, IP = none, Duration = 6 weeks, BC = 11000 dollars/week Activity C, IP = none, Duration = 4 weeks, BC = 8000 dollars/week Activity D, IP = A, B, Duration = 4 weeks, BC = 13000 dollars/week Activity E, IP = B, C, Duration = 3 weeks, BC = 10000 dollars/week What is the total project completion time? What is the total budgeted cost for the project? Construct the table of weekly budgeted cost

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!