Question: please show work Job A Processin Processin g time in g time in Machine 1 Machine 2 16 26 20 33 15 11 25 12

please show work
please show work Job A Processin Processin g time
Job A Processin Processin g time in g time in Machine 1 Machine 2 16 26 20 33 15 11 25 12 148 1 o co wa AWN D E Sequence using 10 Johnson's rule Completiontuime 11 in Machine 1 -> 12 Schedule Completiontuime 14 in Machine 2 -> 15