Question: please show work Report the final SV, CV, CPI and PCIB. Based on your data, what is your assessment of the current status of the

 please show work Report the final SV, CV, CPI and PCIB.

Based on your data, what is your assessment of the current status

of the project? At completion? After 4 time periods the project is

roughly 77% (PCIB) complete and is current getting only 83 cents worth

of work for each dollar spent. The project is currently $10,000 over

please show work

Report the final SV, CV, CPI and PCIB. Based on your data, what is your assessment of the current status of the project? At completion? After 4 time periods the project is roughly 77% (PCIB) complete and is current getting only 83 cents worth of work for each dollar spent. The project is currently $10,000 over budget. There is $3,000 worth of work on critical Activity 5 that has not been completed as planned so the project is behind schedule. Since so much of the project has been completed the project is expected to come in over budget. The forecast cost at completion is $78,000 which is $13,000 over budget. Whether the project will be completed on schedule will depend upon whether Activity 5 can make up for lost time. \begin{tabular}{|l|l|l|} \hline 0 & 1 & 2 \\ \hline 1 & & 1 \\ \hline 1 & 2 & 3 \\ \hline \end{tabular} \begin{tabular}{|l|l|l|} \hline 0 & 2 & 3 \\ \hline 0 & & 0 \\ \hline 0 & 3 & 3 \\ \hline \end{tabular} \begin{tabular}{|c|c|c|} \hline 5 & 7 & 6 \\ \hline 0 & & 0 \\ \hline 5 & 1 & 6 \\ \hline \end{tabular} Status Report: Ending Period 1 Report the final SV, CV, CPI and PCIB. Based on your data, what is your assessment of the current status of the project? At completion? After 4 time periods the project is roughly 77% (PCIB) complete and is current getting only 83 cents worth of work for each dollar spent. The project is currently $10,000 over budget. There is $3,000 worth of work on critical Activity 5 that has not been completed as planned so the project is behind schedule. Since so much of the project has been completed the project is expected to come in over budget. The forecast cost at completion is $78,000 which is $13,000 over budget. Whether the project will be completed on schedule will depend upon whether Activity 5 can make up for lost time. \begin{tabular}{|l|l|l|} \hline 0 & 1 & 2 \\ \hline 1 & & 1 \\ \hline 1 & 2 & 3 \\ \hline \end{tabular} \begin{tabular}{|l|l|l|} \hline 0 & 2 & 3 \\ \hline 0 & & 0 \\ \hline 0 & 3 & 3 \\ \hline \end{tabular} \begin{tabular}{|c|c|c|} \hline 5 & 7 & 6 \\ \hline 0 & & 0 \\ \hline 5 & 1 & 6 \\ \hline \end{tabular} Status Report: Ending Period 1

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!