Question: Please solve it fast !!!!!! c. Calculate the cycle time and draw the precedence graph and find the minimum possible number of workstations. Then arrange

Please solve it fast !!!!!! c. Calculate the

Please solve it fast !!!!!!

c. Calculate the cycle time and draw the precedence graph and find the minimum possible number of workstations. Then arrange the work activities into workstations to balance the line. Assume eight-hour work day, assume output 375 units per day. What is the efficiency of the line? Task Performance time(minutes) Precedence A 12 B 11 6 B D 4 B E 11 A F 5 CD G 9 F H 10 E I 4 GH AC