Question: please try to give the right answer ( thanks in advance ) Activity D takes 14 to complete. After applying the CPM it was found
please try to give the right answer
Activity D takes 14 to complete. After applying the CPM it was found that it is on the critical path. If its early start (ES) is 15 days, what is its early finish (EF)? Question 9 5 pts n a project management problem after employing CPM it was found that A-C-D-F-G- H is the critical path. The times of completing activities F. Gand H are respectively 14, 10 and 23 days. If ES (early start) of Fis 15, what is the EF time of H