Question: please try to give the right answer ( thanks in advance ) na project management problem after employing CPM it was found that A-C-D-E-F- G-H
please try to give the right answer
na project management problem after employing CPM it was found that A-C-D-E-F- G-H is the critical path. The times of completing activities E, F, G and Hare respectively 16, 14, 10 and 23 days. If ES (early start time) of E is 15, what is the (late finish time) LF of H? Question 11 10 pts na project management problem after employing CPM it was found that A-C-D-F-G- H-K is the critical path: K is the last node in the path. The times of completing activities F. G. Hand K are respectively 14. 10. 28 and 25 days. If Es (early start of Fis 23, what is the project completion time. T
( thanks in advance )