Question: Please use Merlin Projects Imagine that you are a project manager for a construction company. You must create a WBS for the Site Preparation phase

Please use Merlin Projects

Imagine that you are a project manager for a construction company. You must create a WBS for the Site Preparation phase of this project. Here is a list of tasks.

Task Title Predecessors Duration
A Contract Approval -- 5
B Site Survey A 5
C Permit Application A 4
D Grading B,C 5
E Sewer Lines B 7
F Base Paving D 3
G City Approval C,F 6
H Final Paving