Question: Please use the following data to answer the subsequent question. QUESTION 30 Use the following information to answer questions 30-33 Task Duration (hours) Due Date
Please use the following data to answer the subsequent question.
QUESTION 30 Use the following information to answer questions 30-33 Task Duration (hours) Due Date 2 5 B 6 8 3 10 D 15 25 E 4 18 Using the SPT priority rule, what order would the tasks be performed? 1 mark ABCDE ACEBD ABCED ODBECA QUESTION 31 What is the "make span" if the SPT priority rule is applied? 2 marks 15 25 30 61 0000 QUESTION 32 What number is closest to the average "flow time" if the SPT priority rule is applied? 2 marks 12 15 30 61 ooo QUESTION 33 What number is closest to the average days late if the SPT priority rule is applied 2 marks 7 5 2 0000