Question: Plese answer quick. A project requires following activities: Activity Time Estimate (days) Immediate Predecessor(s) A 4 - B 4 - C 5 A D 6

Plese answer quick.

A project requires following activities:

Activity

Time Estimate (days)

Immediate Predecessor(s)

A

4

-

B

4

-

C

5

A

D

6

B

E

7

C

F

3

C

G

9

D,E,F

What is the total project duration?

What are the slack times for activities A, B, C and D?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!