Question: Plese answer quick. A project requires following activities: Activity Time Estimate (days) Immediate Predecessor(s) A 4 - B 4 - C 5 A D 6
Plese answer quick.
A project requires following activities:
| Activity | Time Estimate (days) | Immediate Predecessor(s) |
| A | 4 | - |
| B | 4 | - |
| C | 5 | A |
| D | 6 | B |
| E | 7 | C |
| F | 3 | C |
| G | 9 | D,E,F |
What is the total project duration?
What are the slack times for activities A, B, C and D?