Question: PM . 5 6 Massmart has put together a team to improve it's supply chain design. The team has broken the project down into lettered

PM.56 Massmart has put together a team to improve it's supply chain design. The team has broken the project down into lettered activities and their durations in weeks:
\table[[Activity,Duration (weeks),Immediate Predecessor(s)],[A,7,-],[B,17,-],[C,21,-],[D,6,B],[E,2,A],[F,11,E],[G,5,C,D],[H,9,]]
What is the duration of the project (in weeks)?
weeks
What is the project's critical path?
AEF
BDH
BDG
CH
What is the latest start week for activity B?