Question: PM . 5 6 Massmart has put together a team to improve it's supply chain design. The team has broken the project down into lettered
PM Massmart has put together a team to improve it's supply chain design. The team has broken the project down into lettered activities and their durations in weeks:
tableActivityDuration weeksImmediate PredecessorsABCDBEAFEGCDH
What is the duration of the project in weeks
weeks
What is the project's critical path?
AEF
BDG
What is the latest start week for activity B