Question: Please show in excell with formulas please PM.56 Massmart has put together a team to improve it's supply chain design. The team has broken the

Please show in excell with formulas please

PM.56 Massmart has put together a team to improve it's supply chain design. The team has broken the project down into lettered activities and their durations in weeks:

Activity Duration (weeks) Immediate Predecessor(s)
A 8 -
B 18 -
C 22 -
D 6 B
E 5 A
F 13 E
G 3 D
H 10 C,D

What is the duration of the project (in weeks)? weeks What is the project's critical path?

AEF

CH

BDG

BDH

What is the latest start week for activity B? What is the slack time for activity D? weeks If activity E were delayed by 9 week(s) and activity C were shortened by 2 week(s), what would be the project's new critical path?

BDH

CH

BDG

AEF

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!