Question: PM . 5 7 The activities needed to develop a new software application are listed in the following table with the activity times and their

PM.57 The activities needed to develop a new software application are listed in the following table with the activity times and their order in which the activities need to be performed:
Activity Duration (weeks) Immediate Predecessor(s)
A 3-
B 9 A
C 5 A
D 7 A
E 5 A
F 9 B,C
G 10 D,E
H 3 F,G