Question: PM . 6 1 Rob Smith is managing a small project at Boston University. He is under pressure to shorten the overall duration of the

PM.61 Rob Smith is managing a small project at Boston University. He is under pressure to shorten the overall duration of the project by 4weeksand he wants to do so at the lowest cost possible. In order to meet this objective a number of activities must be crashed.
Activity Normal Time (weeks) Crashed Time (weeks) Normal Cost Crashed Cost Predecessor(s)A53$800$1,400-B65$400$500-C65$550$775-D32$900$1,100AE53$1,350$1,950CF63$750$1,650B
What is the duration of the project (in weeks)?
Incorrect
Your Answer:21
What is the target duration of the project (after crashing the project)?
Incorrect
Your Answer:17
By how many weeks should activity A be crashed?
By how many weeks should activity Bbe crashed?
By how many weeks should activity Cbe crashed?
By how many weeks should activity Dbe crashed?
By how many weeks should activity Ebe crashed?
By how many weeks should activity Fbe crashed?
What is the total cost of crashing the project 4 weeks (just the additional cost, not total project cost)?(Display your answer to two decimal places.)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!