Question: PM.53 Sun Oracle is launching a new computer component. The team has broken the project down into activities, with the following durations: Immediate Predecessor(s) Activity

PM.53 Sun Oracle is launching a new computer

PM.53 Sun Oracle is launching a new computer component. The team has broken the project down into activities, with the following durations: Immediate Predecessor(s) Activity A Duration (weeks) 15 B 10 17 A D 5 B E 6 D F 11 A,E G 2 F H 3 CG What is the duration of the project? Number weeks What is the latest start week for activity A? Number What is the slack time for activity B? Number weeks If activity F were shortened by 2 weeks, what would be the new duration of the project? Number weeks