Question: PM.53 Sun Oracle is launching a new computer component. The team has broken the project down into activities, with the following durations: Activity Duration (weeks)
PM.53 Sun Oracle is launching a new computer component. The team has broken the project down into activities, with the following durations:
| Activity | Duration (weeks) | Immediate Predecessor(s) |
|---|---|---|
| A | 16 | - |
| B | 11 | - |
| C | 13 | A |
| D | 4 | B |
| E | 5 | D |
| F | 9 | A,E |
| G | 5 | F |
| H | 5 | C,G |
What is the duration of the project? weeks What is the latest start week for activity C? What is the slack time for activity G? weeks If activity E were shortened by 4 weeks, what would be the new duration of the project? weeks
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
