Question: PM.53 Sun Oracle is launching a new computer component. The team has broken the project down into activities, with the following durations: Activity Duration (weeks)

PM.53 Sun Oracle is launching a new computer component. The team has broken the project down into activities, with the following durations:

Activity Duration (weeks) Immediate Predecessor(s)
A 18 -
B 11 -
C 18 A
D 4 B
E 6 D
F 15 A,E
G 1 F
H 5 C,G

What is the duration of the project? weeks What is the latest start week for activity C? What is the slack time for activity G? weeks If activity E were shortened by 2 weeks, what would be the new duration of the project? weeks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!