Question: PM.53 Sun Oracle is launching a new computer component. The team has broken the project down into activities, with the following durations: What is the
PM.53 Sun Oracle is launching a new computer component. The team has broken the project down into activities, with the following durations: What is the duration of the project?
What is the latest start week for activity C?
What is the slack time for activity E?
If activity D were shortened by 3 weeks, what would be the new duration of the project?
| Activity | Duration (weeks) | Immediate Predecessor(s) |
|---|---|---|
| A | 17 | - |
| B | 9 | - |
| C | 11 | A |
| D | 5 | B |
| E | 4 | D |
| F | 11 | A,E |
| G | 2 | F |
| H | 3 | C,G |