Question: PM.53 Sun Oracle is launching a new computer component. The team has broken the project down into activities, with the following durations: Activity Duration (weeks)

PM.53 Sun Oracle is launching a new computer component. The team has broken the project down into activities, with the following durations:

Activity Duration (weeks) Immediate Predecessor(s)
A 23 -
B 12 -
C 11 A
D 7 B
E 5 D
F 10 A,E
G 3 F
H 6 C,G

What is the duration of the project? weeks What is the latest start week for activity A? What is the slack time for activity C? weeks If activity D were shortened by 2 weeks, what would be the new duration of the project? weeks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!