Question: PM.57 The activities needed to develop a new software application are listed in the following table with the activity times and their order in which

PM.57 The activities needed to develop a new software application are listed in the following table with the activity times and their order in which the activities need to be performed:

Activity Duration (weeks) Immediate Predecessor(s)
A 1 -
B 10 A
C 5 A
D 11 A
E 4 A
F 11 B,C
G 9 D,E
H 4 F,G

What would be the overall duration of the project if activity C were increased by 2 weeks, from 5 to 7 weeks?