Question: PM.57 The activities needed to develop a new software application are listed in the following table with the activity times and their order in which
PM.57 The activities needed to develop a new software application are listed in the following table with the activity times and their order in which the activities need to be performed:
| Activity | Duration (weeks) | Immediate Predecessor(s) |
| A | 1 | - |
| B | 10 | A |
| C | 5 | A |
| D | 11 | A |
| E | 4 | A |
| F | 11 | B,C |
| G | 9 | D,E |
| H | 4 | F,G |
What would be the overall duration of the project if activity C were increased by 2 weeks, from 5 to 7 weeks?