Question: PM.57 The activities needed to develop a new software application are listed in the following table with the activity times and their order in which

PM.57 The activities needed to develop a new software application are listed in the following table with the activity times and their order in which the activities need to be performed:

Activity Duration (weeks) Immediate Predecessor(s)
A 1 -
B 10 A
C 5 A
D 11 A
E 4 A
F 11 B,C
G 9 D,E
H 4 F,G

What is the overall duration of the project (in weeks)? weeks What is the earliest week you could start activity F? (Write the week number in the field below.) What is the earliest week you could finish activity G? What is the latest week you could start activity A? What is the latest week you could finish activity A? What is the slack time for activity G? weeks What would be the overall duration of the project if activity E were increased by 5 weeks, from 4 to 9 weeks? weeks What would be the overall duration of the project if activity D were increased by 5 weeks, from 11 to 16 weeks? weeks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!