Question: point ( s ) possible Submit test In a network diagram, an activity A . should always be something the company has had experience with.
points possible
Submit test
In a network diagram, an activity
A should always be something the company has had experience with.
B is the largest unit of work effort consuming both time and resources that a project manager can schedule and control.
C must always have a single, precise estimate for the time duration.
D is the smallest unit of work effort consuming both time and resources that a project manager can schedule
Stion
and control.