Question: in a network diagram, an activity Part 2 A . is the smallest unit of work effort consuming both time and resources that a project

in a network diagram, an activity
Part 2
A.
is the smallest unit of work effort consuming both time and resources that a project manager can schedule and control.
B.
is the largest unit of work effort consuming both time and resources that a project manager can schedule and control.
C.
must always have a single, precise estimate for the time duration.
D.
should always be something the company has had experience with.