Question: In a network diagram, an activity: is the largest unit of work effort consuming both time and resources that a project manager can schedule and
In a network diagram, an activity:
is the largest unit of work effort consuming both time and resources that a project manager can schedule and control. should always be something the company has had experience with.
must always have a single, precise estimate for the time duration.
is the smallest unit of work effort consuming both time and resources that a project manager can schedule and control.