Question: POM answers are not accepted for this question. Using PERT with three-time estimates, the expected completion time of the project is 45 weeks. The variance
POM answers are not accepted for this question.
Using PERT with three-time estimates, the expected completion time of the project is 45 weeks. The variance of the critical path is 11.
(a) What is the probability that the project will be finished in 44 weeks or less?
(b) What is the probability that the project takes longer than 45 weeks?
(c) What is the probability that the project will be finished between 44 and 46 weeks?
(d) The project manager wishes to set the due date for the completion of the project so that there is a 90% chance of finishing on schedule. What should this due date be?