Question: Precedence Activity A B D E F G A B C D CE ED EF G H Estimated Time (Weeks) 7 8 5 5 6

Precedence Activity A B D E F G A B C D CE ED EF

Precedence Activity A B D E F G A B C D CE ED EF G H Estimated Time (Weeks) 7 8 5 5 6 4 6 5 6 UT - 1. The total duration for the project is: a. 30 weeks b. 25 weeks c. 43 weeks d. 34 weeks 2. The Critical path for the above project is: a. A-C-F-H-1 b. A-C-F-H-I and B-D-E-H-I C. A-D-G-1 d. B-D-E-F-H-I. 3. The slack associated with activity E is: a. 3 weeks b. 4weeks C. 7 weeks d. Oweeks. 4. The slack associated with activity G is which of the following: a. 4 weeks b. 2 weeks C. O weeks d. 3 weeks