Question: Precedence Table Activity ( Task ) Predecessor Activity Duration ( Days ) A None 2 B A 4 C None 1 D B & C
Precedence Table
Activity
Task
Predecessor
Activity
Duration
Days
A
None
B
A
C
None
D
B & C
E
None
F
C & D
G
E & F
H
G & K
I
H
J
None
K
J
L
B
Please use space below to answers questions a to g Show all your work.
a Identify all network diagram pathways and their durations.
Pathways and durations:
b What isare the critical paths and itstheir duration?
Critical path and duration:
c How long will it take to complete the project?
The project will take days to complete.
d What is the float slack time for activity I?
Calculation:
Flow time for activity I:
e What is the float slack time for activity C
Calculation:
Flow time for activity C:
f What is the float slack time for activity E
Calculation:
Flow time for activity E:
g What is the float slack time for activity L
Calculation:
Flow time for activity L:
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock