Question: Precedence Table Activity ( Task ) Predecessor Activity Duration ( Days ) A None 2 B A 4 C None 1 D B & C

Precedence Table
Activity
(Task)
Predecessor
Activity
Duration
(Days)
A
None
2
B
A
4
C
None
1
D
B & C
4
E
None
12
F
C & D
9
G
E & F
3
H
G & K
5
I
H
10
J
None
6
K
J
8
L
B
2
Please use space below to answers questions a) to g). Show all your work.
a) Identify all network diagram pathways and their durations.
Pathways and durations: _
b) What is/are the critical path(s) and its/their duration?
Critical path and duration: _
c) How long will it take to complete the project?
The project will take ____ days to complete.
d) What is the float (slack) time for activity I?
Calculation: _
Flow time for activity I: _
e) What is the float (slack) time for activity C?
Calculation: _
Flow time for activity C: _
f) What is the float (slack) time for activity E?
Calculation: _
Flow time for activity E: _
g) What is the float (slack) time for activity L?
Calculation: _
Flow time for activity L: _

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!