Question: Preceding Activity B D E F Time 8 3 7 3 4 6 Draw the network diagram. Calculate the ES, EF, LS, LF. What is

Preceding Activity B D E F Time 8 3 7 3 4 6 Draw
Preceding Activity B D E F Time 8 3 7 3 4 6 Draw the network diagram. Calculate the ES, EF, LS, LF. What is project completion time? A,B C D 0 E D 0 Start 0 end 0 0 B D F