Question: predecessor A B OMOO Activity Optimistic Most Likely Pessimistic 2 4 8 2 2 2 1 5 7 4 5 6 3 5 9 1

predecessor A B OMOO Activity Optimistic Most

predecessor A B OMOO Activity Optimistic Most Likely Pessimistic 2 4 8 2 2 2 1 5 7 4 5 6 3 5 9 1 0 5 2 7 9 1) The probability that the project will be completed in 22 days 2) The completion time corresponding to a 99% probability A A CB CB | (D-II) Z= D = ' + V6Z Where: D = Desired Project Completion Time Il = Critical Path Duration = Sum of variance of the CP