Question: Predecessor Activity A B Time 3 4 6 A A D B 6 a. Develop an AON network for this problem. b. What is the

Predecessor Activity A B Time 3 4 6 A A D B 6 a.
Predecessor Activity A B Time 3 4 6 A A D B 6 a. Develop an AON network for this problem. b. What is the critical path? c. What is the total project completion time? d. What is the slack time for each individual activity? e. Draw Gantt chart for the project? E B 4 F 4 G D 6 H E, F 8