Question: Predecessor Estimated Time ( days ) A 1 5 B A 1 2 C B 6 D B 5 E C 3 F 8 G
Predecessor Estimated Time
days
A
B A
C B
D B
E C
F
G F
H F
I G
J H
K J
End D
E
I K calculate the Early Start ES Early Finish EF Late Finish LF Late Start LS and Slack for each activity: