Question: Predecessor Optimisitc(a) Most Iikely (m ) Pessimistic (b) Expected value = (a+4m + b)/6 A 1 4 7 4.00 B A 4 8 12 8.00
Predecessor Optimisitc(a) Most Iikely (m ) Pessimistic (b) Expected value = (a+4m + b)/6 A 1 4 7 4.00 B A 4 8 12 8.00 C A 24 25 26 25.00 D A 30 32 34 32.00 E D 10 11 12 11.00 F C,D 3 6 9 6.00 G B,F 3 6 9 6.00 draw network diagram