Question: Prepare a master schedule given this information: It is now the end of week 1 ; customer orders are 25 for week 2,16 for week

Prepare a master schedule given this information: It is now the end of week 1 ; customer orders are 25 for week 2,16 for week 3,11 for week 4, 8 for week 5 , and 3 for week 6 . Use the MPS rule of ordering production when projected on-hand inventory would be negative without production. Suppose that there were 64 pumps in inventory at the beginning of week 1 . A production lot size of 70 pumps is used. (Leave no cells blank - be certain to enter "O" wherever required.)