Question: Prepare forecasts for February through May using the double exponential smoothing model with alpha = 0 . 3 and beta = 0 .

Prepare forecasts for February through May using the double exponential smoothing model with \alpha =0.3 and \beta =0.6.
Assume that the January's unadjusted forecast is 220 and January's trend factor is 10.
Round all answers, including any intermediate steps and calculations, to 3 decimal places.
Period Demand
January 230
February 245
March 250
April 235
May 240
February forecast =
March forecast =
April forecast =
May forecast =