Question: PREVIOUS NEXT Time remaining 00:31:48 PAUSE FINISH Patrick has assumed responsibility for a project that has completed planning and is executing the work packages of
PREVIOUS NEXT Time remaining 00:31:48 PAUSE FINISH Patrick has assumed responsibility for a project that has completed planning and is executing the work packages of the project. In one of the team meeting, a team member questions the validity of the duration that she is assigned to various activities and she seems to be very upset. When the estimate was developed, the team member was not involved as she joined the team later. What action should Patrick take FIRST