Question: PREVIOUS NEXT Time remaining 00:31:48 PAUSE FINISH Patrick has assumed responsibility for a project that has completed planning and is executing the work packages of

PREVIOUS NEXT Time remaining 00:31:48 PAUSE FINISH Patrick has assumed responsibility for a project that has completed planning and is executing the work packages of the project. In one of the team meeting, a team member questions the validity of the duration that she is assigned to various activities and she seems to be very upset. When the estimate was developed, the team member was not involved as she joined the team later. What action should Patrick take FIRST

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!